Chuy Region
Bystrovskaya small hydropower plant rehabilitation
Concept
Key facts
Opportunity
Rehabilitation of the operating plant in Kemin District covers hydromechanical components, electrical equipment and hydraulic gates.
Potential participation
Potential roles:
- Designer: rehabilitation engineering.
- Supplier: runners for units 1–3, shafts for units 2–3, circuit breakers and hydraulic gates.
- Installation contractor: equipment installation and integration.
TechnologyEquipmentEPC
Source note
Information from the supplied materials; the project has not been independently verified.